A second, final layer of asphalt to roads in Gulf Stream’s Core area is “right around the corner,” according to Town Manager Trey Nazzaro.
Roadway Construction LLC had tentatively scheduled the asphalt work for Feb. 23, but Baxter & Woodman Consulting Engineers decided not to allow the contractor to do that until it had finished items on a punch list “to minimize damage to the new asphalt,” Nazzaro said.
The contractor now says it will reach “substantial completion” on March 17 and final completion on May 22.
Nazzaro also said new striping on Sea Road’s curve has made driving on the street more manageable, so the town will not widen that section.
“I was coming around the corner after the lines had been painted in a … full-size sport utility and I had a full-size sport utility on the other end and we were able to navigate that very easily with the lines as a visual cue to understand the width of the road,” Nazzaro said.
— Steve Plunkett