By Steve Plunkett
The city’s dredge contractor is back to work on a beach renourishment project between the Boca Raton Inlet and Red Reef Park.
Weeks Marine Inc. left Boca Raton in April after weather delays let it finish only about 20 per
central beach (5)
Dredging equipment fills the central beach of Boca Raton in late April.
The pipes and bulldozers were removed after work was halted.
Tim Stepien/The Coastal Star
By Steve Plunkett
The city’s dredge contractor has left Boca Raton after compl
By Steve Plunkett
The Greater Boca Raton Beach and Park District plans to hand-deliver a check for $3.7 million — as soon as the City Council finds time to accept it.
The money is half the local cost of renourishing the city’s beaches from the
By Cheryl Blackerby
The renourishment project for Boca Raton’s north beach was plagued with strong winds and big waves that stopped work, but in the end the project was finished ahead of schedule.
Dredging was completed Dec. 13, two weeks shy o
By Cheryl Blackerby
Rough seas halted dredging for the renourishment project at Boca Raton’s north beach Nov. 15. More bad weather delayed dredging during Thanksgiving week.
“We only have eight full days of work left,” said Jennifer Bistyga, co