Work will last until at least Aug. 12 to repave Spanish River Boulevard from its western end to State Road A1A.
“Hopefully the weather is good to us and job will be completed on schedule,” All County Paving project manager Brad Jones said in an email.
“We will do our best to keep traffic moving but some delays should be expected, especially during rush hours,” Jones said.
The project began on July 25 at the boulevard’s terminus with Military Trail.
Workers are grinding 1 inch of the existing asphalt on the first day for each section, then repaving the road surface on the second day.
A tack coat is sprayed first and cannot be driven on until hot asphalt is laid and compacted and the crew reopens the road.
Jones said his company will control as much as possible the dust caused by the grinding. Vehicle access to homes and businesses will be affected during the project’s work hours, 8 a.m. to 5 p.m.
— Steve Plunkett
You need to be a member of The Coastal Star to add comments!
Comments