The Camino Real bridge, scheduled most recently to reopen June 20, is still closed to vehicles, bicycles and pedestrians while construction teams finish a functional inspection of the $8.9 million project.

Sandra Ospina, the project engineer for Palm Beach County, said on July 1 that no date was scheduled yet for when work would end.

“We do not have a definitive date as of today,” Ospina said. “We are hopeful that the opening will happen towards the end of July.”

The bridge closed to land traffic on April 12, 2018. Crews started working nights in mid-May to meet the anticipated June 20 reopening. 

— Steve Plunkett

E-mail me when people leave their comments –

You need to be a member of The Coastal Star to add comments!

Join The Coastal Star

Activity Feed

The Coastal Star posted a blog post
5 hours ago
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a blog post
Wednesday
Mary Kate Leming posted a discussion in DELRAY BEACH
Feb 26
The Coastal Star posted a blog post
Feb 26
Mary Kate Leming posted a discussion in OCEAN RIDGE
Feb 26
The Coastal Star posted a blog post
Feb 26
Mary Kate Leming posted a discussion in DELRAY BEACH
Feb 26
The Coastal Star posted a blog post
Feb 26
Mary Kate Leming posted a discussion in BOCA RATON
Feb 26
Mary Kate Leming posted a discussion
Feb 26
Mary Kate Leming posted a discussion in SOUTH PALM BEACH
Feb 26
The Coastal Star posted a blog post
Feb 26
Mary Kate Leming posted a discussion
Feb 26
Mary Kate Leming posted a discussion in OCEAN RIDGE
Feb 26
Mary Kate Leming posted a discussion in MANALAPAN
Feb 26
More…