The Camino Real bridge, scheduled most recently to reopen June 20, is still closed to vehicles, bicycles and pedestrians while construction teams finish a functional inspection of the $8.9 million project.

Sandra Ospina, the project engineer for Palm Beach County, said on July 1 that no date was scheduled yet for when work would end.

“We do not have a definitive date as of today,” Ospina said. “We are hopeful that the opening will happen towards the end of July.”

The bridge closed to land traffic on April 12, 2018. Crews started working nights in mid-May to meet the anticipated June 20 reopening. 

— Steve Plunkett

E-mail me when people leave their comments –

You need to be a member of The Coastal Star to add comments!

Join The Coastal Star

Activity Feed

Mary Kate Leming posted a blog post
Friday
Mary Kate Leming posted a photo
Friday
The Coastal Star posted a discussion in BOCA RATON
Wednesday
The Coastal Star posted a blog post
Wednesday
Mary Kate Leming posted a photo
Wednesday
The Coastal Star posted a discussion in DELRAY BEACH
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a discussion in MANALAPAN
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a discussion in OCEAN RIDGE
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a discussion in DELRAY BEACH
Wednesday
The Coastal Star posted a discussion in BOCA RATON
Wednesday
Mary Kate Leming posted a discussion
Wednesday
The Coastal Star posted a discussion in BOCA RATON
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a discussion in BOCA RATON
Wednesday
The Coastal Star posted a blog post
Wednesday
The Coastal Star posted a discussion in HIGHLAND BEACH
Wednesday
More…